A project spanning over 10-15 years

In a construction project as uniquely large as The New University Hospital in Aarhus both the preparations and the construction work itself spans over several years.

Following the election of the winning project in December 2007 two organisations have been established; an employer organisation (Projektafdelingen for DNU) and an organisation consisting of the consortium that won the competition (Rådgivergruppen DNU I/S)

The two organisations work together closely and live next door to each other at Hedeager 3, 8200 Aarhus N, Denmark.

The New University Hospital in Aarhus will be fully operational in the beginning of 2019.

The construction of The New University Hospital in Aarhus will take place in two tracks - a northern one and a southern one. In each track construction is divided into five stages; N1-N5 in the northern track and S1-S5 in the southern. Each stage represents one tender package.

Additionally, construction of buildings such as the central Forum, the chapel etc. will also be put out to tender.